China manufacturer of traditional Chinese watchtower structures (古建楼) and garden towers. 2 to 4 story timber pavilion tower designs based on classical Chinese architecture (营造法式). For heritage sites, scenic area towers, museum exhibits, and traditional architecture displays. Engineering certified. OEM custom manufacturing.
| Warranty | Main structure: 10 years | Roof waterproofing: 5 years |
| Delivery | Prefabricated kits: 45-90 days | Complex multi-story: 90-180 days |
| MOQ | 1 unit (custom welcome) |
| Applications | Heritage sites, scenic area observation towers, museum historical buildings, theme park attractions, traditional architecture education, garden landscape focal points |
Heritage sites, scenic area observation towers, museum historical buildings, theme park attractions, traditional architecture education, garden landscape focal points
Standard designs available: 2-story (约6-8m), 3-story (约9-12m), and 4-story (约12-16m). Custom heights available. All structures are engineer-certified for wind load and seismic conditions at the specific site location.
Traditional timber frame with added modern structural engineering: Douglas fir or pine main columns with grain orientation for maximum strength, mortise-tenon joint reinforcement with hidden steel pins, shear walls with OSB sheathing for lateral stability, and steel moment connections at critical joints.
Yes. For seismic zones, we employ a reinforced timber frame: additional steel moment connections at column-base and beam-column joints, OSB diaphragm sheathing on each floor, and a reinforced concrete foundation with anchor bolts. Engineering calculations are provided for local building codes in any country.
Excavate for a full-mat reinforced concrete foundation. For multi-story towers, a significant foundation (full perimeter strip or mat) is required to distribute loads. Anchor bolts are set in the concrete in precise positions matching the ground floor column layout.
Erect the ground floor columns and beams using the numbered kit components. Install all mortise-tenon joints with wood glue and dowels. Verify levelness and plumbness. Install floor diaphragms (plywood/OSB sheathing) for in-plane stiffness.
Working from bottom to top, install each successive floor frame in the same manner. Each floor's columns bear directly on the floor beam below — traditional Chinese layered construction. Install dougong bracket sets at each eave for traditional appearance.
Install the roof frame using the traditional cantilevered bracket system. Apply waterproof membrane across the entire roof area. Install roof tiles (clay or slate) from the eave tiles upward to the ridge. Flash all roof-wall junctions.
Install timber stairs between floors (with optional steel reinforcement for public access towers). Install railings and balustrades to local building code height (typically 900-1100mm). Apply interior and exterior finishes per specification.
Conduct a structural inspection and verify all connections against the engineering drawings. For public towers: arrange for a local engineer to verify the installation. Provide as-built drawings, structural certificate, and maintenance manual.
Contact us with your project requirements — we respond within 2 hours during business hours.
Email: 858069858@qq.com | Tel: +86-138-8336-6528