title: "Repairable Dougong Demonstration Bay, Step by Step"
date: "2026-11-24T03:16:34+08:00"
modified: "2026-11-24T03:19:13+08:00"
url: "https://www.guwanli.com/blog/dougong-demonstration-bay-build-label-repair/"
markdown_url: "https://www.guwanli.com/blog/dougong-demonstration-bay-build-label-repair.md"
content_type: "blog_en"
description: "A dougong demonstration bay succeeds when a visitor can see how the joint carries load Zhongyu Wood Art, 48 years factory experience. Contact: +86 13883366528."
---

# Repairable Dougong Demonstration Bay, Step by Step

A dougong demonstration bay succeeds when a visitor can see how the joint carries load and how a worn arm can be replaced without touching the carved face. It fails when the bay is a decorative wall of brackets that nobody is allowed to open. The difference is not artistry. It is access.

This guide covers module logic, member schedule, assembly order and repair access for a full-size teaching bay.

## What should a dougong demonstration bay prove?

A dougong demonstration bay should prove three things at full size: that the bracket set transfers roof load into the column, that the joint can be taken apart and rebuilt dry, and that one worn member can be replaced without removing the whole assembly.

Those three tests decide the design. A bay that only shows carved profiles is a model. A bay that can be assembled by two people with hand tools is a teaching object. Our workshop has built traditional timber structures for 48 years, and the most common mistake in a display bay is to hide the joint behind a finished panel.

## What does Yingzao Fashi fix, and what does it leave open?

Yingzao Fashi, the building manual completed in 1103 under Li Jie, fixes the module. It defines eight grades of cai, the standard timber section. Each cai is 15 fen high and 10 fen wide, and the width is divided into 10 fen. Grade one is 9 cun by 6 cun; grade eight is 4.5 cun by 3.0 cun. The eight grades let a builder scale a bracket set from a small hall to a palace without inventing a new proportion each time.

## Which members should be visible, and which should be replaceable?

The bay should show one complete load path from the cap block to the purlin. Every member on that path should be visible from at least two sides. Carved queti and gualuo can sit outside the path, because their role is spatial framing, not primary load transfer.

The table below is a starting schedule for a full-size teaching bay. The sizes are working sizes for a demonstration structure, not a universal standard. Adjust them to the selected cai grade and to the roof load.

| Member | Yingzao Fashi term | Role in the bay | Working size | Repair access |
| --- | --- | --- | --- | --- |
| Cap block | Ludou | Collects the bracket arms | 30 x 30 x 20 cm | Open top; no cover board |
| Main arm | Huagong | Cantilevers from the column | 120 cm long | Removable locking pin |
| Inner arm | Nidaogong | Ties the inner tier | 90 cm long | Label on hidden back face |
| Sloping arm | Ang | Provides the lever | 150 cm long | Separate crate; dry joint |
| Short bracket | Queti | Supports the beam end | Span / 4 projection | Hinged access panel |
| Frieze | Gualuo | Frames the bay | 180 x 60 cm | Removable from the front |

Structural members get a removable pin or an open joint. Decorative members get a hinged panel or a front release. Nothing a conservator may need to touch should be fixed with a nail through the show face.

![Carved gualuo frieze panel for a Chinese timber bracket bay](https://www.guwanli.com/wp-content/uploads/2026/09/gualuo-pingfeng_175565.webp)A gualuo frieze frames the bay without carrying the roof load, so it can be released from the front when a carved panel needs repair.

## What is the assembly order for a bay that can be reopened?

Build the bay in the same order a carpenter would build the roof, then mark the order on the parts. The sequence is not a suggestion. It is the maintenance plan.

1. Set the column and check plumb. The bay cannot be corrected later by adjusting the brackets.
2. Place the ludou on the column head and mark its centre line on both axes.
3. Fit the first huagong and the nidaogong. Check that the joint closes under hand pressure, without a mallet.
4. Add the ang and the upper tier. Measure the projection from the column face, not from the carved edge.
5. Fit the queti and gualuo last. These are the parts a visitor will want to touch, so they should be the easiest to remove.

Use a dry fit. A teaching bay should not depend on glue: glue makes a joint quiet, but it also makes the joint invisible. Two people can assemble a single-bay set with hand tools; a three-bay set needs a small team and a lifting plan for the upper tier.

## How should parts be labelled without damaging the show face?

Label every member on a hidden face with a removable tag, and keep a duplicate map in the condition file. Do not stamp the show face. Do not write on a surface that will be re-oiled.

A practical system uses four fields: member code, bay number, install step and mass. The mass field matters more than it looks. A 120 cm arm that weighs 18 kg can be handled by one person; a 150 cm ang at 30 kg should be a two-person lift. The label tells the installer which is which before the crate is open.

If the bay will travel, add a brass tag in a recess and record the tag number. A paper label will disappear. A brass tag will survive a van, a lift and a store room.

## What does a repair path look like in practice?

A repair path has three levels. Level one is wear: a polished handrail, a darkened cap block, a loose pin. Level two is joint decay: a cracked tenon, a split arm, a lifted bearing face. Level three is replacement: a carved queti or a gualuo panel that cannot be repaired without losing the profile.

Design for all three. Keep one spare arm and one spare cap block with the set. A spare part is cheaper than a closed gallery. Record the date of every joint check and photograph the joint before and after a repair.

For the component range and the joint options, see the [dougong brackets for heritage restoration](https://www.guwanli.com/products-en/dougong-brackets-for-heritage-restoration/) page and the [mortise and tenon wood components](https://www.guwanli.com/products-en/traditional-chinese-mortise-and-tenon-wood-components/) range. The earlier note on [dougong and queti naming, repair and replacement](https://www.guwanli.com/blog/dougong-queti-bracket-sets-heritage-repair/) explains the vocabulary in more detail.

## Installation, environment and maintenance

Install the bay on a level floor with a moisture barrier. Keep the room at 45 to 60 percent relative humidity. Avoid a position under direct solar gain, because the top tier will dry faster than the base. Leave a 1 m inspection zone around the column so a conservator can reach every joint.

Check the joint tightness quarterly. Re-oil exposed horizontal faces every 18 to 24 months; shaded vertical faces can go about three years. Do not oil a joint that is meant to stay dry. Dust with a soft brush. Repair a lifted bearing face before it becomes a cracked arm.

Our standard production lead time is 45 to 60 days after drawing approval. The structural warranty is five years, and worldwide installation supervision is available. A single-bay set can ship as numbered members in export crates; a three-bay set needs a sequenced crate plan.

## FAQ

### Is a dougong demonstration bay structural or decorative?

It can be both, but the load path must be real. A bay that carries no roof load is a model. A bay that carries a small demonstration roof is a teaching structure. Decide which one you are buying before the drawings are fixed.

### Can the bay be assembled by museum staff?

Yes, if it is dry-fitted and numbered. A single bay can be assembled by two people with hand tools. A three-bay set needs a small team and a lift plan for the upper tier.

### How long does production take?

About 45 to 60 days after drawing approval, depending on the cai grade, the carving and the finish. The structural warranty is five years.

### What is the minimum order?

One teaching bay is possible. A spare arm and cap block should be ordered with it, because a bay without spares cannot be repaired without stopping the display.

### Which classic should the interpretation panel cite?

Yingzao Fashi is the right primary source for the module and the member names. Cite the eight cai grades and the puzuo tiers. Do not attribute a modern bay dimension to the manual; the manual gives proportions, not a museum layout.

**Planning a full-size craft demonstration?** Call/WhatsApp: +86 138 8336 6528. Zhongyu Woodcraft – 48 Years Traditional Chinese Woodcraft Factory, Nationwide Installation.

[Request the dougong bay member schedule](https://www.guwanli.com/products-en/dougong-brackets-for-heritage-restoration/)

---

**重庆中裕木制工艺品有限公司（中裕木艺 / 古玩里）**

- 官网：https://www.guwanli.com
- 采购咨询：13883366528（微信同号）
- 1978 年建厂 · 48 年木作传承 · 源头工厂直销 · 全国上门安装